Client: Al Ain Farms for Livestock Production – Poultry
Employer: Mena Water
Cost: AED 2 Million.
Project Stages: Detailed Design, Tender Design, Issue for Construction and Supervision
Project Status: Completed
Project Brief:
Al Ain Poultry Farm, located in Al Yaher area roughly 25km from Al Ain, sought to rehabilitate and upgrade its existing industrial wastewater treatment plant to reach 400 m3/day from 240 m3/day treated wastewater.
The technical design prepared by the EPC Contractor was reviewed across two stages, Concept and Detailed Design Review, ensuring the upgrade met the required treatment capacity.
Design Concept:
The review process validated the EPC Contractor’s design approach against the target 400 m3/day capacity, identifying any gaps before construction proceeded.
Services also included construction supervision, ensuring the upgraded treatment plant was delivered in line with the reviewed and approved design.




Built on Trust. Sustained by Excellence.